Brick Work
The brick work moved at a quick pace to cover the Theater Area walls. By the end of the week, the scaffolding was removed to reveal the crew's hard work.
Slider is playing
Slider is playing
Insulation
A lot of steal was cut and put in place over the week. Insulation was added for acoustics in the Music Rooms. Door frames were installed throughout the areas.
Kitchen
The kitchen details started coming together with Back Splash, Exaust, Power, and much more. Temporary walls were put in place separating the Kitchen from the Multi.
Slider is playing
Slider is playing
Power
Miles and Miles of power cables were run through the Kitchen, Theater, and Mezzanine over the week.