banner

Slider is playing
supplies

Supplies moving

More layers were added tot he roof and foam insulation was applied to the kitchen walls.

So many supplies moved into the Multiroom before installed in the new rooms.

Mezzanine

Crews prepared the second floor in the Industrial Arts room. The Mezzanine was prepared for cement to be poured. Steps were the first to take shape. The first view from the Mezzanine showed a Multiroom full of construction supplies.

Slider is playing
mezzanine
Slider is playing
painting

Kitchen

Crews finished up a a little bit of patching before the kitchen got a paint job . The walls got the first coat this week. Then the gridwork started.

Theater

The Theater continued taking shape with the back room walls went up. By the end of the week, the back rooms were finished.

Slider is playing
theater
Slider is playing
hallway

Hallway

It was time to join the existing with the new. The hallway to the lockerrooms and the new Theater and Industrial Arts rooms was opened with a new entrance. The floor was poured creating a smooth path to the new areas.