The Curtain fixture was installed in the Theater, getting ready for grand performances. Scoreboards were added in the Multiroom, just waiting for game nights to light it up. Flooring was installed in the hallway and all the rooms around the Theater. Even more wires were added to the Mezzanine to power our new additions.

Classrooms

The South Wing doors opened up to a new, longer hallway. Classrooms quickly took shape over the week as masonry workers worked fast to build the walls. Conduit was placed as the walls were raised.

Previous Slide
Next Slide
inside
Previous Slide
Next Slide
roof

Roofing

From Trusses to Shingles, crews worked hard through the week to cover the roof. The roof was closed in just in time for the weekend rains to move into the area.